Fast breeder reactor has quite a few firsts (To go with India’s first fast breeder reactor to be ready next year)
February 1st, 2009 - 2:42 pm ICT by IANS ( Leave a comment )Chennai, Feb 1 (IANS) The 500-MW prototype fast breeder reactor (PFBR) fast coming up at Kalpakkam, 80 km from here, has several firsts to its credit.”For the first time in the country’s nuclear power plant construction history, components are being fabricated on site owing to their huge size and weight,” Prabhat Kumar, project director, Bharatiya Nabhikiya Vidyut Nigam Limited (Bhavini) told IANS.
According to him the Rs.35 billion (Rs.3,500 crore/$700 million) plant is also the first nuclear power project to have several huge buildings coming up on a common raft.
The raft measuring 100m x 100m will have buildings housing the reactor, steam generators, fuel rod, electrical, controls, fuel storage, services, switch yard, pump house, turbine generator, sea water and service water pump house, jetty and sea water intake structure.
“It is the largest and deepest (20m) excavated pit next to the sea and dewatering was a major challenge. The 12 concrete pours spread over three and a half months constituted the largest in India,” Kumar said.
PFBR also has the dubious distinction of being the first reactor site to be affected by a tsunami, the one that hit in December 2004.
Sea water and debris carried in by the huge waves filled the huge concrete pit, submerging many equipments including concrete mixing trucks, thereby putting the construction back by a couple of months.
Around Rs.80 million worth of concrete poured in the raft had to be discarded and fresh concrete poured.
Many construction workers were reluctant to start work again, at least till Bhavini officials spent time at the construction site themselves.
The fast breeder project that remained on paper for more than two decades, with many terming it the idle dream of some Indian nuclear scientists, is now a few months away from turning into a reality.
(Venkatachari Jagannathan can be contacted at v.jagannathan@ians.in)
- India's first fast breeder reactor to go critical early 2013 - Jan 21, 2012
- Testing of India's fast breeder reactor by September - Jan 11, 2012
- India's first fast-breeder reactor to cost Rs.5,677 crore - Apr 30, 2011
- Cloudy sky delays installation of reactor component - Sep 16, 2010
- Work on two more fast breeder reactors begins - Sep 14, 2010
- India's first fast breeder reactor to be ready next year - Feb 01, 2009
- India's fast breeder reactor set to achieve fourth milestone - Sep 13, 2010
- Main vessel for India's fast breeder reactor to be built in two weeks (With Images) - Oct 28, 2009
- India's fast breeder reactor nears second milestone - Jun 16, 2009
- Simulator for nuclear power reactor to train technical hands - Aug 18, 2009
- Main vessel for India's fast breeder reactor to be lowered in two weeks (Lead) (With Images) - Oct 28, 2009
- India to talk to France, US for nuclear reactors - Jan 11, 2012
- India's fast breeder reactor gets critical component - Sep 18, 2010
- India's fast breeder n-reactor achieves second milestone (Lead) - Dec 06, 2009
- IGCAR to develop advanced boiler for coal- fired power plants - Sep 06, 2010
Tags: bhavini, concrete pit, construction history, dubious distinction, electrical controls, fast breeder reactor, fuel rod, fuel storage, huge waves, intake structure, nuclear power plant, nuclear power project, nuclear scientists, power plant construction, pump house, steam generators, storage services, switch yard, turbine generator, vidyut