Indian combat jet with indigenous engine further delayed
February 3rd, 2009 - 10:00 pm ICT by IANSBangalore, Feb 3 (IANS) The Indian Air Force (IAF) may have to wait for over a decade to fly a home-grown combat jet powered by an indigenous engine as its full development and flight testing has been further delayed, a top defence official said Tuesday.”The first two LCA (light combat aircraft) squadrons consisting of 20 jets each will be fitted with General Electric (GE) engines. The subsequent squadrons (third, fourth and fifth) could fly with an upgraded version of (the indigenous) Kaveri engine,” Defence Research and Development Organisation (DRDO) Secretary M. Natarajan told reporters here.
The Kaveri engine is to be co-developed by state-owned Gas Turbine Research Establishment (GTRE) and French aeroengine manufacturer Snecma, which was short-listed in 2006. However, a formal agreement is yet to be signed for joint development, testing, transfer of technology and manufacturing.
“Discussions with Snecma have been going on for two years. Instead of going through the cycle of development all over again, we will float an RFP (Request For Proposal) to jointly develop an upgraded version of the Kaveri engine with Snecma. Development and flight testing of the new engine will take at least five-six years,” Natarajan, who is also the scientific advisor to the defence minister, admitted.
Though GTRE initiated the ambitious Kaveri project in 1989 and is estimated to have spent a whopping Rs.20 billion (Rs.2,000 crore/$408 million) over the last two decades on its design and development, insufficient thrust and excess weight have dogged its tests on the ground and in flying conditions.
The IAF, which has placed an order for 20 LCAs with the state-run Hindustan Aeronautics Ltd (HAL), has expressed concerns over the low heat thrust of the GTRE-developed engine and sought its weight reduction to 1,050 kg from 1,250 kg.
“It is true that the air force is concerned with the thrust factor and excess weight of the Kaveri engine. A team of air force engineers is working with GTRE and ADA (Aeronautical Development Agency) in addressing the issues. As an on-going project, the air force will be involved at the point of integrating the upgraded version of the engine with the aircraft,” Natarajan affirmed.
Clarifying that the Kaveri project would not be shelved, Natarajan said DRDO and its associated agencies such as ADA, ADE and GTRE would work on developing a fully indigenous version for mass production of engines that would be required for the LCA project as trainer and naval versions.
“The prototypes of Tejas have already completed 1,000 flight trials. We expect initial operational clearance by December 2010. Weapon trials will begin soon. The first eight aircraft, to be manufactured by HAL in limited series production, are slated to be inducted into IAF fleet by 2011-12,” Natrajan said.
Natarajan was in the city to brief the media about an international seminar on “Aerospace - Perspectives and Trends in Technologies” to be held Feb 9-11, as part of the Aero India-2009 international air show Feb 11-15. DRDO is organising the four-day seminar in association with the Aeronautical Society of India (ASI).
- India test flies naval variant of LCA (Lead) - Apr 28, 2012
- India to form indigenous Tejas fighter squadron by 2013 (Lead, with Images) - Jan 10, 2011
- India's own first supersonic fighter Tejas to join Air Force today - Jan 10, 2011
- India flight tests indigenous jet engine in Moscow - Nov 04, 2010
- India's own fighter jet Tejas to join air force Monday - Jan 09, 2011
- India to flaunt indigenous fighter at aero show - Feb 07, 2011
- India's indigenous fighter to soar high at aero show (Lead, With Images) - Feb 07, 2011
- GE engine set to power India's indigenous combat fighter (Lead) - Sep 30, 2010
- India's own first supersonic fighter Tejas handed to Air Force - Jan 10, 2011
- IAF flies homegrown Tejas fighter jet for operational clearance - Jan 10, 2011
- GE Aviation engine bid lowest for India's jet fighter - Sep 30, 2010
- Kaveri engine completes tests in Russia - May 02, 2011
- India test-flies naval version of LCA - Apr 27, 2012
- IAF wants more improvements in Tejas: Antony - Feb 07, 2011
- Kaveri engine to be installed in 2018 - Sep 16, 2010
Tags: combat jet, defence minister, defence research, development organisation, drdo, excess weight, gas turbine research, gtre, indian air force, kaveri engine, lcas, light combat aircraft, natarajan, request for proposal, research establishment, rfp request, rs 2, snecma, weight reduction, whopping rs