India’s first fast-breeder reactor to cost Rs.5,677 crore
April 30th, 2011 - 6:43 pm ICT by IANSKalpakkam (Tamil Nadu), April 30 (IANS) The upcoming 500 MW prototype fast breeder reactor (PFBR) being built by Bharatiya Nabhikiya Vidyut Nigam Ltd (Bhavini) in this Tamil Nadu town is expected to finally cost Rs.5,677 crore (Rs.56.7 billion), an official said Saturday.
“The nuclear power plant will go on stream next year. The total cost of the project by then will be Rs.5,677 crore. The per MW cost will be around Rs.11 crore which compares well with that of PHWRs (pressurised heavy water reactors) costing around Rs.10.66 crore. The cost per unit of power generated by PFBR will be Rs.4.44,” project director Prabhat Kumar told reporters in Kalpakkam, around 50 km from Chennai.
The original cost of the project was estimated at Rs.3,500 crore and the escalation was due to increase in input costs and construction of residential colony for employees, he said.
The cost was high as this was a single unit while the future units will be cheaper due to revised design, said Prabhat Kumar, adding 80 percent of the cost will be funded by the government and rest from borrowing.
According to Baldev Raj, director, Indira Gandhi Centre for Atomic Research (IGCAR), the sites for two more FBRs have already been identified in Kalpakkam while the other two units can be set up anywhere in India.
They would go critical by 2020, he said.
Raj said many Indian states were demanding nuclear power plant but were now re-looking at the projects after the disaster at Fukushima nuclear power plant in Japan.
On the safety features on IGCAR-designed PFBR, he said it has ‘active and passive’ features which enable the reactor to be shut down immediately. Even if all control and safety rods (CSR) and one diverse safety rod (DSR) fail, or if all DSR and two CSRs fail, the reactor can be shut down within one second, he said.
The IGCAR designed fast reactors has nine CSRs and three DSRs.
- 86 percent work on Kalpakkam N-plant complete: Official - Apr 30, 2012
- Study needed before setting up new nuclear power parks: Scientist - May 01, 2011
- India's first fast breeder reactor to go critical early 2013 - Jan 21, 2012
- Bhavini, fast-breeder reactor operator, to raise Rs.1,200 crore - Jun 10, 2012
- Testing of India's fast breeder reactor by September - Jan 11, 2012
- Bhavini takes measures in favour of fast reactor project - Jun 11, 2012
- Madras Atomic Power Station to restart after shutdown - Aug 20, 2012
- Work on two more fast breeder reactors begins - Sep 14, 2010
- IGCAR to develop advanced boiler for coal- fired power plants - Sep 06, 2010
- India's fast breeder reactor set to achieve fourth milestone - Sep 13, 2010
- Fukushima disaster can't be cited to stop Kudankulam: Scientist - Sep 21, 2011
- India's new fast-breeder on track, nuclear power from September next - May 11, 2010
- India to talk to France, US for nuclear reactors - Jan 11, 2012
- Top level changes at two atomic power operators (Lead) - Jun 01, 2012
- Kudankulam to start full-load power generation by December - Sep 03, 2012
Tags: atomic research, bhavini, csr, csrs, dsrs, escalation, fast breeder reactor, heavy water reactors, igcar, indian states, indira gandhi, indira gandhi centre, input costs, nigam ltd, nuclear power plant, original cost, project director, safety features, single unit, tamil nadu