November 26th, 2008 - 11:09 pm ICT by IANSChennai, Nov 26 (IANS) Power equipment major Bharat Heavy Electricals (BHEL) and Tamil Nadu Electricity Board (TNEB) will jointly set up 1,600 MW super-critical project in Tuticorin district in Tamil Nadu on an outlay of Rs.87 billion (Rs.8,700 crore). The coal-based super-critical project - the state’s first - will be set up by a joint venture company Udangudi Power Corp in which BHEL and TNEB will hold 26 percent stake each and with the financial institutions holding the balance.
The joint venture agreement was signed by the two parties here Wednesday.
The 2×800 MW project to be built on 760 acres will have super-critical boilers, which BHEL will make in collaboration with Alstom and Siemens.
While the first 800 MW unit will go on stream in March 2012, the second unit will start functioning six months later.
The environment impact assessment (EIA) study has been completed and public hearing on the project will be held once the report is prepared.
According to the state government, consultants will be engaged for preparing the detailed project report. The feasibility report has already been prepared.
The Indian Institute of Technology-Madras will prepare the feasibility report for building jetty near the project as the coal will be imported to fire the boilers.
This is the third major joint venture signed by TNEB with a central undertaking after partnering with National Thermal Power Corp and Neyveli Lignite Corp for 1,000 MW projects at Ennore here and Tuticorin.
- Udangudi Power project may not need fresh environment assessment - Feb 27, 2012
- BHEL's exit from Udangudi Power depends on government's offer - Feb 26, 2012
- Tamil Nadu hopes to save Rs.900 crore in Udangudi project - Feb 29, 2012
- BHEL starts supplying super critical boilers - Apr 04, 2012
- Tamil Nadu scraps power joint venture with BHEL - Feb 24, 2012
- Tamil Nadu scraps power joint venture, BHEL surprised (Lead) - Feb 24, 2012
- BHEL signs JV with Madhya Pradesh power plant - Jan 28, 2010
- BHEL still keen on Udangudi power project - Apr 08, 2012
- Tamil Nadu to study LNG power project feasibility - Mar 29, 2012
- BGR-Hitachi power equipment plants to go on stream in 2013 - Sep 16, 2011
- India takes first step towards ultra super-critical boilers - Jan 20, 2012
- Neyveli Lignite blames BHEL for production hitch - May 28, 2011
- Tamil Nadu power generator to float tenders for two power projects - Jan 30, 2012
- National mission on clean coal technologies soon - Oct 12, 2010
- Tamil Nadu to get its first super-critical thermal power plant - Nov 26, 2008
Tags: critical project, electricity board, ennore, environment impact assessment, feasibility report, government consultants, indian institute of technology madras, joint venture agreement, joint venture company, tneb