July 16th, 2010 - 10:58 pm ICT by IANSKolkata, July 16 (IANS) A nuclear power plant is to come up in Haripur in West Bengal’s East Midnapore district, despite some people being against the project, said Srikumar Banerjee, chairman of the Atomic Energy Commission, Friday.
“Haripur is not only the place where resistance was faced to set up a nuclear power plant but such opposition was also being faced in other parts of country like Maharashtra. Haripur is one of the five coastal sites selected by the centre for setting up a Nuclear Energy Park,” said Banerjee.
“We have not been given any deadline from the central government for the project. Land acquisition process will start in 18 months after environmental impact assessment process and geo- technical survey of the land gets completed,” said Banerjee speaking to media persons after delivering the 5th Raja Rammna Lecture at Variable Electron and Cyclotron Centre Kolkata.
Banerjee said they are expecting that construction work for the plant will start after two years and it will take another six years to start operation.
The Department of Atomic Energy has earmarked 650 hectares at Haripur in East Midnapore where generation capacity would be 10,000Mg Wt.
The chairman of Atomic Energy Commission said attempts are being made by the commission to explain to people about the nuclear power plant and people are being taken to other power plants to see for themselves that such an initiative is not hazardous.
At Haripur various groups like the National Fishworkers Forum and a section of the Trinamool Congress leadership have opposed setting up of a nuclear power plant.
Talking about the nuclear energy programme of the government, Banerjee said, “The country will be able to generate about 40,000 MGWT of nuclear energy using both indigenous and nuclear fuel by 2020.”
Earlier in the day, Banerjee met with Chief Minister Buddhadeb Bhattacharjee at state secretariat.
- Atomic agency to approach Mamata over project site - Jun 30, 2011
- Work on Haripur n-plant to begin in 2012-16 period - Mar 02, 2011
- N-reactors do not cause environmental degradation, says AEC - Jan 29, 2010
- Government targets 59,500 MW n-power by 2032 - Jan 11, 2010
- Experts to discuss Jaitapur nuclear project - Nov 28, 2011
- Uranium ore mine commissioned in Andhra Pradesh (Lead) - Apr 20, 2012
- We will scrap Haripur nuclear project: Mamata - Apr 25, 2011
- Atomic energy officials hold talks on Kudankulam n-plant - Nov 04, 2011
- AEC chief Kakodkar downplays terror threat - Nov 17, 2009
- Bengal should set up nuclear plants, SEZs: Assocham - Nov 07, 2011
- 'Indian nuclear facilities safe' - Jun 30, 2011
- Uranium ore mine in commissioned in Andhra Pradesh - Apr 20, 2012
- Manmohan Singh briefed on safety of nuclear installations - Mar 16, 2011
- Construction begins of two 700 MW n-power reactors - Jul 18, 2011
- India's atomic scientists must pass psychological tests for jobs - Jul 30, 2010
Tags: atomic energy commission, bhattacharjee, chief minister, congress leadership, cyclotron centre, energy park, environmental impact assessment, generation capacity, haripur, land acquisition, media persons, midnapore district, nuclear energy, nuclear fuel, nuclear power plant, power plants, state secretariat, technical survey, trinamool congress, west bengal