Neyveli Lignite blames BHEL for production hitch
May 28th, 2011 - 12:27 am ICT by IANSChennai, May 27 (IANS) Integrated mining-cum-power generation company Neyveli Lignite Corporation (NLC) is facing production problem because of the hitch in the boiler provided by power equipment major Bharat Heavy Electricals (BHEL), complained a top NLC official.
“BHEL has failed in its delivery schedules. It is the monopoly India. As a public sector unit (PSU), we have to support BHEL (another PSU). Further we have to go by the lowest bidder in awarding equipment contracts and not by their adherence to delivery schedules and other parameters,” chairman and managing director A.R. Ansari told reporters here Friday.
According to him, NLC’s power units in Rajasthan are not generating power as there is a design failure in BHEL’s boilers.
“We had told BHEL that their boiler should be capable of handling lignite with an ash content ranging between eight to 30 percent. BHEL initially agreed and later was not able to meet the expectation. There is a design failure in their boiler,” Ansari claimed.
BHEL had supplied the 2×125 MW Circulating Fluidised Bed Combustion (CFBC) boilers to NLC for its power project in Rajasthan.
Both the units were dedicated to the nation in June 2010. However, the boilers started facing problems and power generation had to be halted for nearly a year.
Similarly, at Neyveli in Tamil Nadu there has been an inordinate delay in the commissioning of 2×250 MW CFBC power unit.
According to Ansari, the first unit will be commissioned next month and the second unit in 2012.
It is not only CFBC power equipments, even normal boilers and other equipments which is BHEL’s forte is getting delayed, NLC officials fume.
“There is six months’ delay in delivery of equipments for our 1,000 MW thermal project in Tuticorin in Tamil Nadu, promoted in joint venture with Tamil Nadu Electricity Board (TNEB),” K.Sekar, NLC’s director (Finance), said.
He said: “BHEL is biting much more than it can chew, putting others into problems. Contractual penalties for not sticking to delivery schedules do not work.”
BHEL officials were not available for comments.
–Indo Asians News Service
vj/prv/vt
- BHEL looks at South African market for CFBC boilers - Jan 31, 2012
- Techincal problems continue to dog Neyveli lignite unit - Apr 10, 2012
- Neyveli Lignite's 250 MW boiler operating at full load - Feb 07, 2012
- Neyveli Lignite to add 250 MW power this fiscal - Dec 24, 2011
- Neyveli Lignite set to light 250 MW unit - Nov 21, 2011
- BHEL to commission piping plant in Tamil Nadu in April - Jan 30, 2012
- Bharat Heavy Electricals dismisses Neyveli Lignite's charges - May 29, 2011
- Neyveli Lignite's power plant to be ready this fiscal - Apr 04, 2010
- Neyveli Lignite seeks to commission 250 MW unit in Rajasthan - Oct 10, 2009
- Neyveli Lignite to power capacity to 4,640 MW by 2015 - Jul 08, 2011
- Neyveli Lignite to go alone on Gujarat power project - May 27, 2011
- Neyveli Lignite plans to enter power transmission sector - May 27, 2011
- Jayalalithaa asks Prime Minister for power from central pool - Jun 06, 2011
- Neyveli Lignite to expand its thermal power projects in Tamil Nadu - Jan 10, 2012
- BHEL to expand boiler division capacity to 20,000 MW - Apr 05, 2011
Tags: adherence, ansari, ash content, boiler, boilers, combustion, delivery schedules, design failure, director finance, equipment contracts, generating power, joint venture, lignite, nlc, power generation company, public sector unit, sekar, tamil nadu electricity board, tneb, tuticorin