India’s fast nuclear reactor project costs rise 40 percent
August 14th, 2009 - 2:31 pm ICT by IANS ( Leave a comment )By Venkatachari Jagannathan
Chennai, Aug 14 (IANS) India’s first fast breeder nuclear reactor, coming up at Kalpakkam near here to produce 500 MW of power, is facing a cost overrun of over 40 percent, but officials hope it will achieve criticality by September 2011 after a year’s delay.
Escalation in material and labour costs, changes in component design and the tsunami of December 2004 pushed up costs from Rs.3,500 crore to Rs.5,000 crore, according to Nuclear Power Corp chairman S.K. Jain, who is also chairman and managing director of the state-owned Bharatiya Nabhikiya Vidyut Nigam (Bhavini), the company setting up the Kalpakkam project.
“The project report sent to the cabinet in 2002 was prepared like any other government department project; cost estimates were made without factoring taxes that are applicable for corporate entities like Bhavini. Between 2002 and 2009, the costs have escalated several times,” Jain told IANS.
Admitted project director Prabhat Kumar: “The project faced several surprises.”
Apart from the tsunami that hit the Indian shores in 2004, Kumar said, construction of a tunnel under the sea got delayed on account of an unexpected soft patch of soil, which had to be reinforced before work could proceed.
The entire construction technique had to be altered - after tests that ate up time and money.
Kumar said 90 percent of civil works and component fabrication on the nuclear reactor side has been completed.
He said Rs.1,850 crore has already been spent on the project. Bhavini has now started discussions with domestic financial institutions for raising the requisite funds.
As per plans, 76 percent of the project cost will be funded by the government, four percent by the Nuclear Power Corp, and the balance will be debt.
(Venkatachari Jagannathan can be contacted at v.jagannathan@ians.in)
- India's first fast-breeder reactor to cost Rs.5,677 crore - Apr 30, 2011
- India's new fast-breeder on track, nuclear power from September next - May 11, 2010
- India's first fast breeder reactor to go critical early 2013 - Jan 21, 2012
- NPCIL tying up with state-run firms for n-power - Jul 22, 2011
- Testing of India's fast breeder reactor by September - Jan 11, 2012
- Work on two more fast breeder reactors begins - Sep 14, 2010
- Fast breeder reactor has quite a few firsts (To go with India's first fast breeder reactor to be ready next year) - Feb 01, 2009
- IGCAR to develop advanced boiler for coal- fired power plants - Sep 06, 2010
- Cloudy sky delays installation of reactor component - Sep 16, 2010
- India's fast breeder reactor set to achieve fourth milestone - Sep 13, 2010
- Main vessel for India's fast breeder reactor to be built in two weeks (With Images) - Oct 28, 2009
- Construction begins of two 700 MW n-power reactors - Jul 18, 2011
- India's first fast breeder reactor to be ready next year - Feb 01, 2009
- India's fast breeder reactor nears second milestone - Jun 16, 2009
- India's fast breeder reactor gets critical component - Sep 18, 2010
Tags: component design, component fabrication, construction technique, corporate entities, cost estimates, criticality, crore, domestic financial institutions, escalation, government department, jagannathan, labour costs, managing director, nuclear power, nuclear reactor, prabhat kumar, project director, reactor project, s k jain, tsunami of december 2004