Hold officials liable for Himachal project delay: CAG
April 14th, 2011 - 6:30 pm ICT by IANSShimla, April 14 (IANS) The Comptroller and Auditor General (CAG) has asked the Himachal Pradesh government to fix financial liabilities on officers of state-run electricity board for heavy cost and time overruns in setting up a hydropower project in the state - delayed for over ten years.
The national auditor has also taken serious note of lack of action against the erring officials by the government for wasting hundreds of crores of rupees of public money in the 126 MW Larji project on the Beas river in Mandi district, completed after a delay of 125 months.
The CAG has recommended action against the officers, besides recovery of interest on Rs.5.83 crore paid to the contractors. It suggested imposition of a penalty of Rs.1.54 crore on the officers responsible for the mess.
“It (the project) was completed at a cost of Rs.1,293.69 crore against the estimated cost of Rs.168.85 crore,” said the report, tabled in the state assembly last week.
It said the envisaged per unit and per mega watt costs of 24.47 paise and Rs.1.34 crore increased to Rs.2.40 and Rs.10.27 crore respectively, which was perhaps the highest ever spent on a run-of the river project.
The project was approved by the Planning Commission in 1987 at a cost of Rs.168.85 crore. The actual work started in 1990-91 with a completion schedule of September 1996. But the project was also completed after a delay of 10 years.
The reasons for cost overruns were delay in taking up construction works, change of design, overpayment to favourite contractors, mismatch in construction activities of civil and electro-mechanical and high rates.
- Some rail projects delayed for two decades: Auditor - Aug 05, 2011
- 'Warship delays not linked to Mazagon Docks upgrade' - Nov 23, 2011
- From streetscaping to lights - CAG slams Delhi government - Aug 05, 2011
- CAG slams MPs for irregularities in area funds - Mar 18, 2011
- Crucial dates on Kalmadi's appointment escaped CAG's gaze: Congress - Aug 09, 2011
- Kashmir hydro project faces delay due to Pakistan (Lead) - Nov 18, 2010
- PMO, Delhi CM indicted for Commonwealth Games flaws (Roundup) - Aug 05, 2011
- Rs.19,000 crore approved for J&K; rail line - Jan 04, 2012
- Engineers being made scapegoats in CWG mess: Council - Aug 11, 2011
- Dhumal seeks work on pending rail projects - Feb 19, 2012
- Assam gas project cost rises to Rs.8,920 crore - Nov 16, 2011
- CWG infrastructure: The flip side (To go with 'Zipping through flyovers, Metro') - Sep 30, 2011
- CAG slams 'avoidable' expenditure for Connaught Place renovation - Aug 05, 2011
- '251 delayed projects to cost 23.45 percent more' - Aug 19, 2011
- India-Pakistan water dispute escalates power project costs - Nov 18, 2010
Tags: beas river, completion schedule, comptroller, construction activities, construction works, crore, crores, electricity board, financial liabilities, himachal pradesh government, hydropower project, mega watt, overruns, paise, public money, rs 1, rs 2, rupees, shimla, state assembly