Dhumal details loss due to delay in hydropower project
December 8th, 2010 - 11:35 pm ICT by IANSDharamsala, Dec 8 (IANS) With the delay in the commissioning of a $1,300 million hydropower project in Himachal Pradesh, there is a production loss of more than 4,000 million electric units annually, Chief Minister Prem Kumar Dhumal said here Wednesday.
“Since the award of the project Dec 1, 2006, there has been a production loss of 4,320 million units annually. So far, 17,280 million units have been lost,” Dhumal said in a written reply in the state assembly.
He said the project (awarded to Dutch firm Brakel Corp) is currently under litigation.
“The case has been listed for hearing in the Supreme Court Jan 24, 2011. The government filed its reply in the court July 22,” Dhumal said while replying to a question by Congress legislator G.S. Bali.
Brakel Corp had challenged an earlier ruling of the Himachal Pradesh High Court, which Oct 7, 2009, ordered cancellation of the allotment of the 960 MW Thopan-Powari-Jangi hydropower project in Kinnaur district to it on a petition filed by Reliance Infrastructure, one of the bidders.
“We allow the writ petition and quash the decision of the council of ministers dated Nov 25, 2008, as being arbitrary, illegal and irrational,” the high court then said.
Subsequently, the state government decided to invite fresh bids for the project. It even decided to forfeit the company’s upfront premium of Rs.280.69 crore ($60 million) deposited with the government for delaying the implementation of the project.
The state government signed an agreement with Brakel in 2008, two years after the project was awarded to the Dutch company, for starting the pre-construction activities for the project. The company had already carried surveys and investigations at the site.
The government, as per the agreement, is entitled to get 12 percent free power from Brakel. The project requires an investment of more than $1,300 million.
- Himachal losing Rs.100-cr a year on delayed hydro project - Apr 05, 2011
- Himachal losing Rs.150 crore a year on power project - Aug 23, 2011
- Himachal wants to re-allot hydro-power project to Brakel - Jul 25, 2010
- Himachal penalises Dutch firm Rs.280 cr for project delay - Dec 05, 2009
- Court notice to Himachal government over power project - Mar 17, 2010
- Himachal court cancels allotment of hydropower project to Brakel - Oct 07, 2009
- Himachal Pradesh to issue show-cause notice to Brakel - Oct 22, 2009
- Brakel gets more time to respond to Reliance Energy's petition - Mar 31, 2009
- Probe demanded into Himachal hydropower project contract - Oct 09, 2009
- Himachal court advances hearing on Brakel's hydropower project - Apr 23, 2009
- Himachal signs power project agreement with Brakel - Apr 09, 2009
- Himachal allows Dutch firm to begin power project work - Nov 25, 2008
- Himachal Pradesh defers decision on controversial power project - Nov 03, 2008
- Brakel gets four weeks to reply on Reliance Energy petition - Jan 08, 2009
- Himachal Pradesh High Court dismisses Reliance Energy petition - Oct 30, 2008
Tags: 60 million, allotment, bali, bidders, cancellation, chief minister, construction activities, council of ministers, dutch company, dutch firm, jan 24, legislator, litigation, mw, oct 7, pre construction, state assembly, state government, upfront, writ petition