Coal supply disruption shuts power units, hits NALCO plant
February 23rd, 2011 - 12:07 am ICT by IANSBhubaneswar, Feb 22 (IANS) Coal supply disruption triggered by an agitation in Orissa’s Angul district has led to shutting down of units of the National Thermal Power Corporation (NTPC) and may force aluminium manufacturer NALCO to cut output, officials said Tuesday.The supply from Mahanadi coalfields through railways rakes stopped since Feb 17 following an economic blockade at Talcher in Angul district by local residents demanding stoppage of all trains passing through the area.
The coal stock at the NTPC coal fired power plant at Kaniha in Angul district fell to about 8,000 tonnes and the power generation was down to 400 MW since Sunday, the plant’s executive director R. Venkateswaran told IANS.
The 3,000 MW capacity plant which supplies power to country’s eastern and southern region through the state grid consumes 57,000-58,000 tonnes of coal every day for full operation of all its six units of each 500 MW.
Venkateswaran said five units have already been shut and if the situation does not improve in a day or two, they may have to shut the remaining one unit.
Similarly the coal supply has been stopped to the aluminium plant of NALCO at Angul. A senior company official said the aluminium smelter has only a stock of about two lakh tonnes of coal which can last for only about ten days.
Although the shortage has not yet affected aluminium production, the official said situation will be grim if the coal stock get exhausted.
“We will take stock of the situation in a day or two and will decide out further course of action,” the official told IANS.
While the state-run NTPC is India’s largest power producer, the Bhubaneswar-headquartered NALCO is Asia’s largest integrated aluminium producer.
- Coal shortage forces NALCO to cut aluminium production - Sep 10, 2011
- Employees seek end to coal crisis at NALCO plant - Sep 16, 2011
- Government allows NALCO to mine coal - Aug 21, 2011
- Nalco seeks energy banking ties with GRIDCO - Jul 20, 2011
- NALCO signs agreement with mines ministry - Mar 16, 2011
- NALCO continues output cut as coal supply stays thin - Oct 20, 2011
- NALCO floats tender to buy two lakh tonne coal - Jul 31, 2010
- NALCO to import two lakh tonnes coal - Oct 21, 2011
- NALCO introduces aluminium T-ingots - Mar 24, 2011
- NALCO gears up for expansion,to enter metal and power sectors - Oct 01, 2010
- Nalco puts Indonesia smelter project on hold - Aug 15, 2012
- NALCO to finalise Indonesia coal deal by January - Oct 02, 2010
- National Aluminium on a major diversification drive: Chairman - Jul 28, 2011
- NALCO hikes aluminium prices - Jun 01, 2011
- Telangana collieries strike hits power supplies in south India - Sep 15, 2011
Tags: agitation, aluminium plant, aluminium producer, aluminium production, aluminium smelter, angul, coal fired power, coal fired power plant, coal supply, economic blockade, kaniha, mw, ntpc, orissa, power generation, power producer, railways, stoppage, supply disruption, tonnes